GTC 541/2012 Earth Works for Mega Reservoirs at Umm Slal

Enabling earth works for Primary Reservoirs & Pumping Station (PRPS) Site 2 (Umm Slal), which includes bulk excavation over of an area of some 350,000 m2 to an average depth of 6 meters,   including crushing and stockpiling of   67 500 m3 and off-site disposal of 2 003 332 m3 of excavated material.

Awarded to: M/s Bin Omran Trading & Contracting